Significant progress has been made on the Catalina Project since the first phase of works commenced in 2011. The following has been achieved to date:

Construction

Civil works have been completed to Stages 1 – 15, 17A, 18 and 25 (Catalina Beach) comprising over 909 lots.  Bulk earthworks for the Central Precinct have been completed for Stages 1 - 18.  Phase 1 bulk earthworks for the Western Precinct (Catalina Beach) were completed in September 2015, allowing for civil works to be progressed for 200 lots at Catalina Beach which included Stage 25.  

The Marmion Avenue/Aviator Boulevard and Neerabup Road/Roulettes Parade intersections have all been completed.  The intersections provide an easy and direct entry into the Catalina Project and to the Catalina Sales Office and Builders Display Village.

The Catalina Project has 713 homes completed and another 122 currently under construction. A range of lot types and sizes have been produced supporting a diverse mix of housing, from large 4 x 2 family homes on lots in the order 450m² to terraced cottage style housing on lots of 225m².

Catalina Sales Office

The Catalina Sales Office has been operational since May 2014. It is located at 39 Aviator Boulevard and comprises a modern and contemporary house showing best practice housing techniques.

Operating hours are as follows:

Monday - Wednesday: 12pm - 5pm

Thursday: Closed

Friday - Sunday: 12pm - 5 pm

Sales and Marketing

As of August 2017, 909 lots have been released for sale at Catalina, with status of the lots being as follows:

  • Sold - 846 lots
  • Settled -  809 lots

Further information on available lots can be obtained from the Catalina Estate website.

Builders Display Village

The Catalina Builders Display Village (2) was completed in February 2016 and comprises 23 houses by Perth’s leading builders and contains impressive, contemporary and innovative homes. The Display Village offers the latest housing designs including a substantial range of two-storey housing. The Display Village will be in operation until October 2018 at which point a new Display Village in Catalina Beach will be opened.

Landscaping

To date a number of parks have been completed at Catalina, including:

The Stage 4, 8, 10, 11 and 13 parks, Neerabup Road verge works and the Aviator Entry off Marmion Avenue. All these areas provide important local amenities for residents and demonstrate the quality of the Catalina Project.

More recently a significant upgrade to Aviator Boulevarde and the entry of Marmion Avenue has been undertaken. The Greenlink along Aviator Boulevard is continuing to be progressed and currently has two exercise nodes along the path. The Greenlink will form a high amenity pedestrian link between the three Precincts of the Catalina Estate.